Glen Eagle Reports on Operations and Smelting

Ad blocking detected

Thank you for visiting CanadianInsider.com. We have detected you cannot see ads being served on our site due to blocking. Unfortunately, due to the high cost of data, we cannot serve the requested page without the accompanied ads.

If you have installed ad-blocking software, please disable it (sometimes a complete uninstall is necessary). Private browsing Firefox users should be able to disable tracking protection while visiting our website. Visit Mozilla support for more information. If you do not believe you have any ad-blocking software on your browser, you may want to try another browser, computer or internet service provider. Alternatively, you may consider the following if you want an ad-free experience.

Canadian Insider Ultra Club
$432/ year*
Daily Morning INK newsletter
+3 months archive
Canadian Market INK weekly newsletter
+3 months archive
30 publication downloads per month from the PDF store
Top 20 Gold, Top 30 Energy, Top 40 Stock downloads from the PDF store
All benefits of basic registration
No 3rd party display ads
JOIN THE CLUB

* Price is subject to applicable taxes.

Paid subscriptions and memberships are auto-renewing unless cancelled (easily done via the Account Settings Membership Status page after logging in). Once cancelled, a subscription or membership will terminate at the end of the current term.

(TheNewswire)



 

Montreal, Quebec – TheNewswire - October 5, 2021 Glen Eagle Resources Inc. - (TSXV:GER) (“Glen Eagle” or the “Company”) is pleased to announce that the recent ramp-up of its operations at Cobra Oro’s gold processing plant in Honduras, a wholly owned subsidiary of the Company, have yielded excellent results which are reflected by the least downtime ever since the inception of the plant five years ago.

 

Karl Trudeau, COO, comments: “All efforts have been put in place to properly ramp-up the plant in a professionnal way involving the revision of the primary crushing system, the realignment of the ball mill gear system and maintenance of the pumps, including the main vacuum pump system leading to the Merrill Crowe gold precipitation process.”

 

Indeed, downtime caused by mechanical failures has been very rare in the past two months and should improve further with a substantial amount of spare parts expected to be delivered in the near future. As a consequence of these major improvements, Cobra Oro is adding a third shift to production and working closely with its ore providers to increase tonnage and grade for better throughput.

 

In conjuction to the ramp-up, the Company was able to smelt a dore bar valued at approximately $170,000 Canadian dollars representing three weeks of production time. Additional data  on gold-silver recoveries and production throughput will be released when the Company receives its upcoming metallurgical balance.

  

Jean Labrecque, President

Glen Eagle Resources Inc

2075 Victoria Street

Suite 201

St-Lambert, Québec

J4S- 1H1

514-808-9807

 

“Neither TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.”  Values in the news release are quoted in canadian dollars.

 

Copyright (c) 2021 TheNewswire - All rights reserved.