Ad blocking detected

Thank you for visiting CanadianInsider.com. We have detected you cannot see ads being served on our site due to blocking. Unfortunately, due to the high cost of data, we cannot serve the requested page without the accompanied ads.

If you have installed ad-blocking software, please disable it (sometimes a complete uninstall is necessary). Private browsing Firefox users should be able to disable tracking protection while visiting our website. Visit Mozilla support for more information. If you do not believe you have any ad-blocking software on your browser, you may want to try another browser, computer or internet service provider. Alternatively, you may consider the following if you want an ad-free experience.

Canadian Insider Ultra Club
$500/ year*
Daily Morning INK newsletter
+3 months archive
Canadian Market INK weekly newsletter
+3 months archive
30 publication downloads per month from the PDF store
Top 20 Gold, Top 30 Energy, Top 40 Stock downloads from the PDF store
All benefits of basic registration
No 3rd party display ads
JOIN THE CLUB

* Price is subject to applicable taxes.

Paid subscriptions and memberships are auto-renewing unless cancelled (easily done via the Account Settings Membership Status page after logging in). Once cancelled, a subscription or membership will terminate at the end of the current term.

Titanium Achieves First CVW™ Horizon Project Milestone

CALGARY, Alberta, May 15, 2018 (GLOBE NEWSWIRE) -- Titanium Corporation Inc. ("Titanium" or the "Company") (TSX-V:TIC) is pleased to announce the achievement of Milestone 1 of the front end engineering design ("FEED") phase of its CVW™ Horizon Project. The FEED project is being supported by Emissions Reduction Alberta ("ERA") through the award of grant funding of up to the lesser of $5.0 million or 50% of engineering design. Titanium and Canadian Natural are funding $1.5 million and up to $3.7 million, respectively.

ERA funding provided under the ERA Methane Challenge is provided in stages during the project as the Company meets and reports against predetermined milestones established under the ERA Contribution Agreement. 

"The project team is working closely with engineering firms Stantec and IHC Robbins and engineering design is progressing very well, on time and on budget," commented Scott Nelson, President and Chief Executive Officer of Titanium.  "ERA's funding support has been instrumental in accelerating this phase of the project."

The project has incurred $1.1 million of costs to the end of March, 2018, the Milestone 1 period. Project activities have included identifying locations and tie-ins for the new facilities, preparing detailed scopes of work for requests for proposals and selection of the engineering contractors.

About Titanium Corporation Inc.
Titanium's CVW™ technology provides sustainable solutions to reduce the environmental footprint of the oil sands industry. The Company is working with Canadian Natural Resources Limited on front end engineering design for potential deployment of CVW™ at Canadian Natural's Horizon oil sands site. The Company's technology reduces the environmental impact of oil sands tailings while economically recovering valuable products that would otherwise be lost. CVW™ recovers bitumen, solvents and minerals from tailings, preventing these commodities from entering tailings ponds and the atmosphere; volatile organic compound and greenhouse gas emissions are materially reduced; hot tailings water is improved in quality for recycling; and residual tailings can be remediated more readily. A new minerals industry will be created commencing with the production and export of zircon, an essential ingredient in ceramics. The Company's shares trade on the TSX Venture Exchange under the symbol "TIC". For more information, please visit the Company's website at www.titaniumcorporation.com.

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this release.

 

For further information, contact:

Scott Nelson
President & CEO
Tel: (403) 561-0439
Email: [email protected] 

David Feick
Investor Relations, LodeRock Advisors
Tel: 403-831-7557
Email: [email protected]

Comment On!

140
Upload limit is up to 1mb only
To post messages to your Socail Media account, you must first give authorization from the websites. Select the platform you wish to connect your account to CanadianInsider.com (via Easy Blurb).