Antioquia Gold Cisneros Operations Update

Ad blocking detected

Thank you for visiting CanadianInsider.com. We have detected you cannot see ads being served on our site due to blocking. Unfortunately, due to the high cost of data, we cannot serve the requested page without the accompanied ads.

If you have installed ad-blocking software, please disable it (sometimes a complete uninstall is necessary). Private browsing Firefox users should be able to disable tracking protection while visiting our website. Visit Mozilla support for more information. If you do not believe you have any ad-blocking software on your browser, you may want to try another browser, computer or internet service provider. Alternatively, you may consider the following if you want an ad-free experience.

Canadian Insider Ultra Club
$500/ year*
Daily Morning INK newsletter
+3 months archive
Canadian Market INK weekly newsletter
+3 months archive
30 publication downloads per month from the PDF store
Top 20 Gold, Top 30 Energy, Top 40 Stock downloads from the PDF store
All benefits of basic registration
No 3rd party display ads
JOIN THE CLUB

* Price is subject to applicable taxes.

Paid subscriptions and memberships are auto-renewing unless cancelled (easily done via the Account Settings Membership Status page after logging in). Once cancelled, a subscription or membership will terminate at the end of the current term.

Calgary, Alberta--(Newsfile Corp. - July 6, 2023) - Antioquia Gold Inc. (TSXV: AGD) (OTC Pink: AGDXF) ("Antioquia Gold", the Company or the "Corporation") is pleased to provide a summary of June 2023 production results for its Cisneros mining operation, and to announce the progress of other ongoing projects.

Production Summary and Operations Update:

During June, 3,428 troy ounces of gold were produced at the Cisneros mining operation, with a recovery of gold to concentrate of 97.43% during the month.

Monthly Operational Details

Gold production and metallurgical recovery:


JanuaryFebruaryMarchAprilMayJuneTotal/average
Gold Production (Tr Oz)3,7273,9662,5002,8292,6683,42819,118
Gold Recovery (%)96.14%96.77%96.06%97.11%97.8%97.43%96.9%

 

Underground Development:

UG Developments (Meters)JanuaryFebruaryMarchAprilMayJuneTotal
Guayabito Mine5426656206447046263,801
Guaico Mine5245245245365675283,203
Total1,0661,1891,1441,1801,2711,1537,004

 

Third Party Mineralized Material: During June, 1,831 tonnes of third-party mineralized material with an average gold grade of 12.49 g/t were purchased, representing 20% of the monthly gold production.

Mr. Gonzalo De Losada, CEO of Antioquia Gold, stated "After facing three months of challenges related to environmental authority issues and limited tailings storage capacity, we have successfully resolved these challenges and restored normal operations. Currently, our process plant is operating at full capacity, and we are optimistic about a more favorable second semester after overcoming these hurdles."

Readers should be cautioned that the Corporation's decision to move forward with the construction and production of the Cisneros Mine is not based on the results of any pre-feasibility study or feasibility study of mineral resources demonstrating economic or technical viability. Readers are referred to the Cisneros Report for details on independently verified mineral resources on the Cisneros Project. Since 2013, the Corporation has undertaken exploration and development activities; and after taking into consideration various factors, including but not limited to: the exploration and development results to date, technical information developed internally, the availability of funding, the low starting costs as estimated internally by the Corporation's management, the Corporation is of the view that the establishment of mineral reserves, the commissioning of a pre-feasibility study or feasibility study at this stage is not necessary, and that the most responsible utilization of the Corporation's resources is to proceed with the development and construction of the mine. Readers are cautioned that due to the lack of pre-feasibility study or feasibility study, there is increased uncertainty and higher risk of economic and technical failure associated with the Corporation's decision. In particular, there is additional risk that mineral grades will be lower than expected, the risk that construction or ongoing mining operations will be more difficult or more expensive than management expected. Production and economic variables may vary considerably, due to the absence of a detailed economic and technical analysis in accordance with NI 43-101. Project failure may materially adversely impact the Corporation's future profitability, its ability to repay existing loans, and its overall ability to continue as a going concern.

Qualified Persons

Roger Moss, Ph.D., P.Geo., Consultant to Antioquia Gold, is the qualified person as defined by National Instrument 43-101 and has reviewed and approved the technical information provided in this news release.

For further information on Antioquia Gold Inc. contact:
Gonzalo de Losada - CEO
Thomas Kelly - Director
Antioquia Gold Inc.
Email: [email protected]
www.antioquiagoldinc.com
Phone 57 604 6041948

Neither the TSX Venture Exchange nor its Regulation Services Provider (as that term is defined in the policies of the TSX Venture Exchange) accepts responsibility for the adequacy or accuracy of this press release.

Reader Advisory Forward-Looking Statements:

This press release contains "forward-looking information" within the meaning of Canadian securities legislation. This information and these statements, referred to herein as "forward-looking statements", are made as of the date of this press release and the Corporation does not intend, and does not assume any obligation, to update these forward-looking statements, except as required by law.

Forward-looking statements relate to future events or future performance and reflect current expectations or beliefs regarding future events and include, but are not limited to, statements with respect to: the completion of the Rights Offering and the use of proceeds of the offering. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, using words or phrases such as "expects", "anticipates", "plans", "projects", "estimates", "assumes", "intends", "strategy", "goals", "objectives", "schedule" or variations thereof or stating that certain actions, events or results "may", "could", "would", "might" or "will" be taken, occur or be achieved, or the negative of any of these terms and similar expressions) are not statements of historical fact and may be forward-looking statements.

Forward-looking statements are made based upon certain assumptions by the Corporation and other important factors that, if untrue, could cause the actual results, performances or achievements of Antioquia to be materially different from future results, performances or achievements expressed or implied by such statements. Such statements and information are based on numerous assumptions regarding present and future business prospects and strategies and the environment in which Antioquia will operate in the future, including the accuracy of any resource estimations, the price of gold, anticipated costs and Antioquia's ability to achieve its goals, anticipated financial performance, regulatory developments, development plans, exploration, development and mining activities and commitments. Although management considers its assumptions on such matters to be reasonable based on information currently available to it, they may prove to be incorrect. Additional risks are described in Antioquia's most recently filed Annual Information Form, annual and interim MD&A and other disclosure documents available under the Corporation's profile at: www.sedar.com.

By their very nature, forward-looking statements involve inherent risks and uncertainties, both general and specific, and risks exist that estimates, forecasts, projections and other forward-looking statements will not be achieved or that assumptions do not reflect future experience. We caution readers not to place undue reliance on these forward-looking statements as a number of important risk factors could cause the actual outcomes to differ materially from the beliefs, plans, objectives, expectations, anticipations, estimates, assumptions and intentions expressed in such forward-looking statements.

To view the source version of this press release, please visit https://www.newsfilecorp.com/release/172631

Comment On!

140
Upload limit is up to 1mb only
To post messages to your Socail Media account, you must first give authorization from the websites. Select the platform you wish to connect your account to CanadianInsider.com (via Easy Blurb).